HSIP: Jewel Lake Road Widening, 88th Avenue to Strawberry Road

Project Schedule


 

Schedule

 

Draft Design Study / 65% Design: Completed January 2016
Environmental Documentation: July 2014 - February 2016
Final Design Study / 95% Design: Completed October 2016
Final Plans and Specifications: August 2017
Right of Way Appraisal and Acquisition: November 2016 - August 2017
Construction: 2018 (dependent on ROW impacts)